Key takeaways
- Answer the three Model for Improvement questions (aim, measures, changes) before the first test.
- Write down a prediction for every test. Without one, the Study step has nothing to compare against.
- Start with one patient, one clinician or one shift, and scale up only when the change works.
- Plot a few data points over time instead of relying on a single before-and-after number.
What a PDSA cycle is
Plan-Do-Study-Act (PDSA) is a structured way to test a change in the real work setting and learn from the result. The Institute for Healthcare Improvement (IHI) describes it as shorthand for testing a change on a small scale, such as one patient or one day, then planning the test, carrying it out, observing the results and acting on what was learned.
The cycle traces back to Walter Shewhart's specification–production–inspection cycle of 1939. W. Edwards Deming reworked it over several decades and, late in his career, insisted on "Study" rather than "Check": the third step is about learning from the result, not just checking whether the change was carried out.
- Plan: state what the test is for, predict what will happen and why, and decide who, what, where and when, including what data you will collect.
- Do: run the test and note problems and anything unexpected.
- Study: compare the data with your prediction and summarize what you learned.
- Act: adopt, adapt or abandon the change, and plan the next cycle.
Sources
PDSA and the Model for Improvement
In healthcare, PDSA is usually used inside the Model for Improvement, developed by Associates in Process Improvement and promoted by IHI. The model asks three questions before any testing begins:
- What are we trying to accomplish? (the aim)
- How will we know that a change is an improvement? (the measures)
- What change can we make that will result in improvement? (the changes to test)
The questions set the direction and the PDSA cycles do the testing. Teams move back and forth between them as tests show what works. Regulators recognize the approach: CMS's QAPI guidance for nursing homes recommends a problem-solving model such as PDSA for performance improvement projects and publishes a PDSA template, though it does not require that particular tool.
Sources
- Institute for Healthcare Improvement, "Model for Improvement" (developed by Associates in Process Improvement) (opens in a new tab)
- Centers for Medicare & Medicaid Services, "QAPI at a Glance" (opens in a new tab)
- Centers for Medicare & Medicaid Services, "PDSA Cycle Template" (QAPI tool) (opens in a new tab)
ImprovementFlow
Improvement Projects
In Improvement Projects, each PDSA test is recorded with its anticipated effect and then its actual effect, inside the A3 it belongs to, so the Study step has a place to live and the next cycle starts from what the team learned.
What good PDSA practice looks like
A 2014 systematic review in BMJ Quality & Safety checked 73 published healthcare PDSA projects against five features of the method: iterative cycles, prediction-based tests, small-scale testing, data over time and documentation. Fewer than 20% (14 of 73) documented a sequence of iterative cycles. Only 4 of the 47 studies analyzed in detail stated an explicit prediction, and only 2 of the 73 met the criteria for all five features. Much of what gets called PDSA is a single, large change with no prediction.
Those five features make a practical checklist:
- Write down a prediction before each test, so the Study step has something to compare against.
- Start small, with one patient, one clinician or one shift, and increase the scale only when the change works.
- Collect a little data at regular intervals and plot it over time, rather than relying on one before-and-after number.
- Link the cycles: each test should build on what the last one taught.
- Record each cycle briefly while it is fresh.
Example: a sequence of tests for a new handoff tool
An illustrative sequence for a unit trying a bedside handoff checklist:
- Cycle 1: one pair of nurses uses the checklist for one patient at one evening handoff. Prediction: it adds little time and surfaces at least one item the usual report misses. Learning: two prompts are confusing.
- Cycle 2: revised wording, three pairs of nurses, one shift. Learning: it works, but the card is hard to find at the bedside.
- Cycle 3: the whole night shift for one week, with a simple tally of items caught and minutes taken.
- Cycle 4: day shift and a weekend, where conditions differ, before the unit decides whether to adopt it.
Where PDSA tends to stall
On paper or in a spreadsheet, the Plan section gets filled in carefully because it happens in a meeting. The Do section gets a few notes. The Study section, which means going back to the data after the test has run, often never gets written, because nothing brings the sheet back at the right time. Without it, the team is running Plan-Do-Act and hoping for the best.
Culture matters as much as paperwork. Teams test more, and learn faster, when leaders treat "the test didn't work as expected" as useful information rather than failure.
How ImprovementFlow supports PDSA
- Each test of change is recorded on the A3 it belongs to, with its anticipated effect and then its actual effect once the test runs.
- Plan steps carry an owner, a team and a due date.
- The project's linked metrics show starting, current and goal values next to the tests.
- Follow-up reviews record whether a change was sustained after implementation.